Worrying lack of results from HAFF

worrying lack of results from HAFF

February 2026

Two years after Labor sold the Housing Australia Future Fund (HAFF) as the $10 billion answer to the rental affordability crisis, the scoreboard is brutal: about 895 social and affordable homes completed by the end of December — just over 2% of the promised 40,000 within five years.

That is not a “slow start”. It is a program crawling while the housing shortage sprints ahead.

Housing Australia, the agency running HAFF, says the pipeline is building: 9,485 dwellings under development, more than 8,000 in planning, and “up to 3,000” homes to be made available during 2026.

It also insists the latest tender round will run more smoothly after governance problems and a high‑risk, hurry‑up launch that has already attracted scrutiny.

But Australians don’t live in pipelines. They live in houses — and the delivery record is wafer-thin.

Even within HAFF’s own early commitments, progress is underwhelming. The 895 completions represent roughly 4.8% of the 18,650 homes commissioned across the first two funding rounds. Nearly two years after the first round began, funding had been finalised for only 3,315 homes — less than 10% of the total 40,000 target.

If this is the nation’s flagship, it’s barely left the harbour.

The agency once argued that buying “turnkey” dwellings from third‑party developers would get roofs over heads faster than building from scratch. Yet the numbers tell a different story. Of the 895 homes delivered last year, 556 came from applicant‑led projects where the successful bidder developed the housing itself. Only 339 were turnkey. One of the largest completions, Assemble’s Swift Walk in Melbourne, delivered 272 social and affordable homes (plus 90 market homes) and was proponent‑led.

Turnkey procurement can deliver efficiency when you’re effectively buying volume. Applicant‑led projects can be better targeted — placed where community housing providers already support tenants, rather than pushing people to greenfields sites with fewer services.

But whichever model you prefer, the headline remains: the “fast” pathway hasn’t made HAFF fast.

Now HAFF’s third round tightens the screws. Successful projects must have homes operational by June 30, 2029 — about three and a half years from tender to completion — shorter than the five years allowed in round one. The compressed timetable is likely to favour turnkey deals, even as Housing Australia insists there is still time to develop projects from the ground up.

Community housing providers are uneasy about the financing settings. Round three lifts the concessional, zero‑interest loan component to 20%, but it can be paired with up to 70% senior debt from Housing Australia. That leaves providers staring at a 90% debt stack that becomes interest‑bearing when the 25‑year contract ends — just as funding runs out.

The risk is obvious: some providers may be forced to sell housing to repay loans, shrinking the affordable stock HAFF is meant to expand.

Housing Australia says providers will be in a stronger position to retain stock. Maybe. But after two years and 2% delivered, the public is entitled to ask when this flagship starts looking like progress.

Latest news:

Billions Wasted and Corruption Allegations Mount November 2026 Victoria’s infrastructure program has become one of the greatest examples of government […]

Bloated Public Service Is Becoming a National Liability November 2026 Australia has a serious productivity problem, a government spending problem […]

Queensland hits the brakes on a potential Snowy 2.0 Disaster November 2026 At last, we have a government showing some […]

Read more:

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top